Renovation of every green at Barceló Montecastillo Golf Resort

The 18 greens on the course, plus the pitching green and the putting green, renovated in 23 days with the course open for play.

The project

Barceló Montecastillo Golf Resort, in Jerez de la Frontera (Cádiz). We renovated every green on the course (all 18, plus the pitching green and the putting green) in 23 days, with the course open for play. We are still carrying out improvements and works on the course today.

Stripping and shaping

Stripping the greens
Stripping the greens
Stripping the greens
Stripping the greens
Stripping the greens
Rotavating the surface profile of the greens
Shaping the greens with a Sand Pro
Shaping the greens
Compacting and settling the shaped greens

Turfing

Turf delivery
Laying turf on the greens
Laying turf on the greens
Laying turf on the greens
Laying turf on the greens
Laying turf on the greens
Laying turf on the greens
Laying turf on the greens by hand
Turfing the greens

Finishing

Top-dressing the greens by hand
Brushing by hand to work the sand into the turf
Top-dressing the greens by hand
Top-dressing the joints by hand
Fertilising the greens
Fertilising the greens

The team

The site team that renovated 21 greens in 23 days.

Project details

Type of project
Golf, Renovation
Location
Jerez de la Frontera (Cádiz)
Year
2023
Duration
23 days
Works
  • Stripping the greens
  • Shaping and compaction
  • Turfing