Football and rugby

Pitch at the Francisco de la Hera stadium (Extremadura UD)

A new pitch in 7.5 days: removal of the topsoil, new drainage, irrigation and pumping, a new root zone and turf.

El Estadio Francisco de la Hera con el tepe nuevo avanzando sobre el terreno de juego, visto desde la grada.

The project

Complete rebuild of the pitch at the Francisco de la Hera stadium, in Almendralejo (Badajoz), in 2017. We removed the existing topsoil, 15 centimetres of it; installed brand-new drainage, as the pitch had none; fitted new irrigation and pumping; laid a new root zone and turfed the pitch until it was green from end to end.

All in 7.5 days.

The project on video

Time-lapse by Javier Jiménez García from the club’s webcam, published with permission. Also on YouTube.

Project details

Type of project
Football and rugby
Location
Almendralejo (Badajoz)
Year
2017
Duration
7.5 days
Works
  • Removal of the old topsoil (15 cm)
  • New drainage
  • New irrigation and pumping
  • New root zone
  • Turf across the whole pitch